Mobile Mix Concrete
Mobile Mix Concrete

Call (860) 646-7687
or email
Info@mobilemixconcrete.net

Mobile Mix Concrete


 

 

How To Guide from Mobile Mix Concrete

Step 1
Pads and sidewalks: first remove grass and topsoil. If area is not well drained a base of compacted pea stone, recycled process, or trap rock is recommended. This will help prevent water from washing out the base or freezing and heaving the concrete.

Sono tubes (Deck piers): Dig holes to required depth, check with local building department for the required depth. Plumb and level tubes before backfilling. It is rare that the truck can “shoot” the concrete into piers. We have found it much faster and neater for you to wheelbarrow the concrete and shovel it in. One full wheelbarrow will fill one 10” diameter pier 42” deep and two 8” piers 42” deep.

Step 2
Using 2”x4”'s or 2”x6”'s frame out the area. Level the forms and steak the outside of the forms to secure them. Measure and cut a board to “Screed” the concrete after pouring it.

Step 3
Measure the area to be formed. A one inch difference in a 10'x10' pad means approximately 21% more concrete, so measure carefully. Calculate the amount of concrete needed. There are two calculators on this site for you use.

Step 4
Make sure you have the correct concrete tools for you particular job. Using the correct finishing tools is essential to ensure a quality project.

Step 5
Call Mobile Mix Concrete to verify and order the amount of concrete that you need.

Step 6
Fill forms either by direct delivery from out trucks for by wheelbarrow.

Step 7
“Screed” the concrete. Screeding is the process of smoothing the concrete by using a 2x4 in a sawing motion over the concrete. This levels the concrete with the surrounding forms. It also recommended that the forms be gently tapped from the outside to eliminate any air pockets.

Step 8
“Float” the concrete to smooth out any remaining rough areas. Be careful not to “overwork” the concrete. At this time you can also edge the concrete with and edging tool.

Step 9
After all “bleed water” has evaporated from the surface, finish with a sharp edged “steel trowel”. This will produce a very smooth finish. A “broom finish” is recommended for areas that may get wet and slippery such as: sidewalks and pool decks. This is accomplished by dragging a broom across the concrete after using the “steel trowel” for the final time. A final pass with the edging tool will give the broom finish a clean cut off at the edges.

Step 10
The process of the concrete setting up is a chemical reaction not a “drying out” of the concrete. Water is an important part of this reaction. It is important that the concrete be kept moist especially in hot weather. Concrete that cures too fast may be weak which would cause it to flake, peel, or dust.


Mobile Mix Concrete is a proud member of the Greater Manchester Chamber of Commerce
 
Home | About Us | FAQs | Delivery Areas | How To Guide
How To Diagram | Who Uses Us | Calculators | Contact Us